RAZ-400KW intermediate frequency power supply---+---furnace shelf (combination)

  • Description

Induction Heating Power Supply--Safety Operation Guide


1. Before starting the machine, first check whether the water, gas and electricity are connected. After connecting, the following operations can be performed;

2. The operator must prepare corresponding insulating shoes, gloves, etc.

3. The operator must have the corresponding electrical knowledge.

4. Before the equipment is overhauled, the electric switch must be pulled off to confirm that the power supply is disconnected, and then the discharge treatment is carried out, and then the overhaul card is hung up, and the overhaul is repeated.

5. Before starting the machine, first make sure that the waterway is normal and all parts of the equipment are normal before starting the machine.

6. Turn on the first gear filament first, then turn on the second gear filament after five minutes, and then send the high voltage after another five minutes.

7. Before sending high voltage, make sure that the output adjustment potentiometer is in a small position, and then send high voltage, and adjust the output voltage to the working voltage.

8. After confirming that there is a workpiece, you can press the heating button to make the equipment work, but no-load heating is not allowed.

9. If there is an abnormality in the equipment during work, the power supply must be disconnected immediately, and the reason should be checked before working again.

10. After the equipment is finished working, first disconnect the heating, then disconnect the high voltage, then turn off the filament and disconnect the power supply.

11. After the equipment stops working, wait for five minutes before disconnecting the water source.

12. During the operation of the equipment, if there is a temporary need to leave, it must be done. People leave the machine and stop it. It is not allowed. The machine is still working when there is no one.


weekly maintenance

1. When taking over the shift, check the flow of the cooling water outlet pipe of the equipment for abnormal phenomena. For equipment that uses evaporative cooling tubes, it is necessary to check whether the water level of the distilled water tank is qualified;

2. When taking over, check whether the cooling air volume of the glass shell and core column of the electronic tube and other ventilation and heat dissipation facilities are normal;

3. Check whether the contacts of each AC contactor are ablated and whether the wiring is loose;

4. Measure the insulation resistance of cooling water. The ground resistance of the anode of the water-cooled tube should be greater than 300K ohms;

5. The cooling water pipes of the electronic tube grid and the filament are mostly rubber tubes, which are easy to age and should be carefully checked. For the rubber tube that is aging and about to break, it should be updated in time;

6. Do a cleaning and dust removal on the inside of the chassis, wipe off the dust of each high-pressure porcelain bottle and insulating pillars, and pay attention to the cleaning of the dust filter on the air inlet of the fan. Prevent the air intake from being blocked and reduce the air output.


Semi-annual maintenance

1. Check whether the insulation performance of the low-voltage electric control circuit is qualified;

2. Use a megohmmeter to detect the insulation resistance of high-voltage devices such as high-voltage rectifier transformers, high-voltage cables, and high-voltage silicon stacks, and the value should meet the requirements;

3. Check the roundness of the inner tube of the water jacket of the electronic tube and the height of the positioning protrusion, so as to prevent the partial overheating of the anode caused by the deviation of the tube. And check whether there is scaling at the water jacket outlet and inlet pipe joints, and whether the anti-corrosion electrode is normal; 4. Check the set current value of each overcurrent relay;

5. For connecting conductors with high temperature during operation, such as filament lead wires, soft connecting wires for welding transformer primary coils, etc., if there is poor oxidation contact, additional treatment should be made;

7. Thoroughly clean the hidden places such as the top of the cabinet and the cable trench.


Link to this article:http://m.mortgage-hk.com/en/product/product20181026142.html
Previous:NO!
Next:NO!

Recommended Products

HOME About Us Product News Case Video Advantages Contact
主站蜘蛛池模板: 精品国产一二 | 91麻豆精品一二三区在线 | 极品美女销魂一区二区三区 | 青青青草视频 | 成色网| 亚洲美女性生活视频 | 精品1区2区 | 午夜欧美福利 | 中文字幕人妻一区二区在线视频 | 亚洲综合一二三 | 久久视频一区 | youjizz.com中国 | 2022精品国偷自产免费观看 | 中文字幕人妻一区二 | 粉嫩小泬无遮挡久久久久久 | 亚洲av电影一区 | 天天干天天操天天射 | 五月激情啪啪 | 无码人妻少妇伦在线电影 | 国产激情网址 | 日本最新中文字幕 | 白丝女仆被免费网站 | 国产一区二区在线播放 | 日韩黄色在线 | 爱情岛论坛自拍亚洲品质极速最新章 | 色午夜婷婷 | 依依av| 国产aa毛片 | 国产综合久久久久 | 海量av资源 | 少妇人妻一区二区三区 | 亚洲视频免费在线 | 最新中文字幕视频 | 日本精品在线播放 | 成年人看的免费视频 | ts人妖另类精品视频系列 | 经典av在线| 伊人久久久 | 自拍偷拍18p| 操人视频免费 | 欧美三级午夜理伦 | 91狠狠干| 在线观看免费视频一区 | 国产成人久久精品麻豆二区 | 日本一区二区三区精品 | 成人黄色在线视频 | 一本色道久久综合亚洲精品图片 | 久久视频在线 | 欧美日韩激情视频在线观看 | 黄色在线观看av | 欧美午夜视频在线观看 | 97在线精品视频 | 国产成人短视频在线观看 | 亚洲一区二区三区网站 | 里番精品3d一二三区 | 欧美性受xxxx黑人 | 亚欧三级 | 他揉捏她两乳不停呻吟动态图 | 中出av在线 | 影音先锋欧美资源 | 黄色小网站在线观看 | 一级少妇毛片 | 国产精品99精品无码视 | 成人网色 | 99伊人| 天天插日日干 | 久操视频网 | 日韩熟女一区二区 | 欧美日韩无 | 国产精品xxxx喷水欧美 | www日本高清视频 | 久久精彩免费视频 | 欧美一级三级 | 黄网在线免费观看 | 亚洲黄色片网站 | 日本亚洲色大成网站www久久 | 一级黄色影院 | 亚欧在线 | 中文字幕在线观看网址 | 麻豆视频在线免费看 | 91打屁股 | 有码在线播放 | 日韩色图片 | 一级国产黄色片 | 网红av在线| 亚洲国产高清国产精品 | 中文字幕一区二区三区在线视频 | 九九久久国产 | 欧美精品一线 | 美景之屋电影免费高清完整韩剧 | 久久久久人| 1区2区3区在线观看 久久久久高潮 | 日韩电影在线观看一区二区 | 91美女视频在线观看 | 国产欧美一级 | 国内精品久久久久久久影视简单 | 亚洲自拍网站 | 国产第一毛片 | 成人黄页 |